To date Auldyn Construction and its many sub-contractors have completed: 

Highway Construction
280 metres of highway construction has been completed on the seaward side of Queens Promenade 
500 metres of lower layers of road construction installed on the landward side of Loch Promenade.

Water Trunk Main Installation
515 metres out of 2,100 metres of 355mm diameter installed
370 metres out of 640 metres of 180mm diameter installed

Electric Installation
High Voltage circuits installed and made live from:
Strathallan sub-station to Queens (200 metres)
Loch Promenade SS to Howard Street SS (300 metres)
Empress SS and Villa SS (500 metres)
HV ducting installed between Queens SS and Switzerland Rd (200 metres)

Gas Main Installation
350 metres of 315mm diameter PE main installed

Telecom Installation
Approximately 800 metres of new ducting installed

Tram Rail Installation
Over 1,800 metres of tram line have been installed

Since the re-start post Christmas a lot of preparatory work has taken place prior to installation of various mains, kerbing and paving. 


Updated on 31 January 2020