Updates

September 2021 completion date

The contractor delivering the Douglas Promenade Refurbishment Scheme, Auldyn Construction, has now advised that the planned completion date has moved to the end of September. 

Despite increased levels of resource being deployed, the contractor’s latest delivery programme shows a further delay of one month. In order to help speed up completion, the Department of Infrastructure has taken parts of the project and is delivering these with other resources.

The Department remains committed to working proactively with Auldyn to provide as much support as possible during the final phases of the construction programme.

Following completion, Auldyn has a further four weeks to correct defective work, and the company is working alongside the rail corridor designer, Burroughs Stewart Associates, to prepare a proposal to correct the concrete defect before the end of this period.

Infrastructure Minister Tim Baker MHK said: ‘Although I am extremely disappointed at this setback, the Department will continue to do all it can to assist Auldyn in this final push for the end. ‘There have been a number of unforeseen challenges which must be acknowledged, including a difficulty relating to COVID restrictions in accessing labour resources from off-Island. ‘A pragmatic and constructive dialogue continues with the company on finishing as soon as possible, but we will not allow the quality of the finished product to be compromised at this stage.’

He added: ‘I recognise the effort and commitment of all parties to get this project concluded, and appreciate that many people, particularly those involved in businesses, are looking forward to our community enjoying its newly-refurbished promenade.’

Updated on 14 July 2021
Stay in the loop
Connect with us