The MyProm team feel it is important to let you know what's happening so below are last week's works and what we are doing this week:

Last week the works included:

Continuing with the laying and preparation of unbound stone material for the rail slab;

Excavation for the rail slab has reached the Palace Hotel and will stop until the concrete rail slab has begun and is well progressed;

Utility service road crossings continue to be installed;

Trial hole at Mona Drive undertaken;

 Road markings on Summerhill installed.

 This week we are:

Casting the first section of concrete rail slab;

Continuing with Utility service road crossings;

Laying Service ducting and a water main commencing on Harris Promenade.

The Puffin crossing at the old Imperial Hotel site is now live too!

The sequence of phasing plans have all the dates (please bear in mind these will be updated regularly so timings may shift slightly). They are all available by clicking this link

We will be starting to work on Loch Promenade in the next couple of weeks so keep checking what's happening. We are continuing to liaise with all key stakeholders - residents, businesses, motorists, delivery drivers (including Isle of Man Post Office, pedestrians etc and are keen to work together to find solutions.

Please sign up for our newsletter, drop into the public office at the Sea Terminal, Douglas (sign posted on the ground floor) between 9am-4pm Monday to Friday or email myprom@gov.im. You can also get updates via our social media feeds of Facebook, Twitter or Instagram @mypromisleofman.

We realise these works are having an impact and are working hard to find solutions to minimise inconvenience. Thank you for your patience and understanding.

 

Updated on 12 February 2019