Keeping you in the picture about the refurbishment of Douglas Promenade

more parking on Loch Promenade

We have added more on-street parking alongside the opening of the walkway parking. While some areas of the road and footway have finished surfacing, the majority is still only partly complete. The final highway surface is still to be installed north of the Howard Street junction. Pedestrian crossings need to be finalised including the installation of granite marker posts at Victoria Street. Final footway surfacing is still required (mainly on the seaside) along with the erection of the new lighting columns throughout the Marine Gardens.

The Project Team regularly re-assess the working sequence and programme to meet the needs of businesses and the community, currently in the run up to Christmas and also beyond until the scheme is complete. 

Updated on 10 December 2020